Drywall and other miscellaneous work

Before we get to drywall I’m going to hit on a few items that have been in process but don’t really warrant their own post.

Interior Doors

All of our interior doors are pre-hung, which means they arrive on site already hinged and set within a frame. Here’s one of our finish framers working his magic on a bathroom door.

DSC_6665_alt1

During the install process the door is taken off its hinges and the frame is attached to the rough opening.

DSC_6674_alt1

Once the frame is set plumb and level the door is then placed back on the hinges.

DSC_6691_alt1

After the door panel is in place and found to be swinging smoothly, it is typically taken back off the hinges and set aside for safe keeping. All our interior doors are solid core, with the exception of the closets.

DSC_6549_alt1

boxing in the eaves

Due to a bit of missed coordination with our roofer we had a ton of shiners at the eaves. A shiner occurs when the pointy end of the nail comes through the back of the material into which it had been driven. We had originally intended to leave the rafters exposed, but given the mess that was now visible overhead we went with plan B and boxed in the eaves.

DSC_7099_alt1

I actually prefer the boxed in detail from an aesthetic and maintenance perspective. The original design of exposed rafter tails is a more traditional approach and stemmed from concerns that the planning commission would deem our project too modern. Turned out that wasn’t such an issue during review but I never circled back and changed the detail in the construction documents.

DSC_6557_alt1

Bob and my sister Jill, along with Trish’s dad, Greg, spent the good part of a week framing in the eaves and getting a coat of primer on. A true family affair!

DSC_7101_alt1

DSC_7677_alt1

Finished up just before stucco got underway. More on the stucco install soon.

tile at shower walls

I feel the need to at least mention this area of work given the amount of time that Bob has already put in. I’m going to wait for a dedicated post on tile work when the floors are complete, but here’s a sneak peak.

DSC_7153_alt1

DSC_7108_alt1

Bob is easily our hardest working subcontractor. He probably needs a raise.

drywall

Drywall has been in process now for a few weeks. Overall it has gone really well and the guys are almost done. In fact, Units A and B already have the first coat of paint up and we’re off to the races on casework install, but more on that later. Units C and D will finish up by Tuesday of this week and hopefully be painted by the end of the week. We’re getting pretty excited at this point because suddenly there’s only finish work left on the interior. Here’s the photos of the beautiful mess.

DSC_7134_alt1
prep: QR = QuietRock (space-age sound dampening drywall between units)
DSC_7137_alt1
prep: window sills will be painted MDF, window seat will match floor
DSC_7145_alt1
prep: bringing finish down to flush out with the tile module below
DSC_7139_alt2
prep: narrow posts between windows to be black stained wood

DSC_7425_alt1

DSC_7421_alt1

DSC_7442_alt1
the install process gets a “bit” messy
DSC_7438_alt1
block will remain exposed at the basement

DSC_7684_alt1

DSC_7662_alt1
kerfed jamb (drywall metal turns directly into the door frame) = no casing needed
DSC_7657_alt1
I thought about doing the math on how many lbs of this stuff went onto the wall. It’s a lot.

DSC_7809_alt1

DSC_8319_alt1
skillz
DSC_7858_alt1
these steel angles will receive our “floating” treads
DSC_8348_alt1
our finish is a “light skip trowel” – very clean, and a lot less expensive than perfect

DSC_8352_alt1

DSC_8357_alt1

 

1 Comment

  1. Great progress Tyler! It is really coming together. It is great that your dad loves to do home projects.