Framing part two

I’m calling it on the second half of framing.

There’s still a few interior walls to frame up, miscellaneous blocking and shear panels to go in, but the envelope is basically there. When we left things in late October the deck level walls were just framed. From that point upper level floor joists quickly followed, enclosing the living spaces on the deck level. Here’s a few shots of the interiors:

DSC_3971_alt1
living room window at unit B – we’re pretty jealous of the view of the old oak tree here
DSC_4253_alt1
living space in Unit D
DSC_4237_alt1
view from our living room to the kitchen/dining room at the deck level – so much light!
DSC_4289_alt1
looking up at the wall-to-beam connection

Here’s the framing getting started on the upper level walls:

DSC_3968_alt1
entry doors with windows above at unit A (left) and B (right)

DSC_4282_alt1

DSC_3976_alt1
trusses staged at the end of the space

We are using scissor trusses at the upper level roof. The top chord of each truss is is a 3:12 slope while the bottom chord is 1.5:12. Scissor trusses are a great way to create a shallow vault at the interior while still saving critical inches in overall structure height.

DSC_3993_alt1

DSC_3996_alt1
smooth-faced ACX plywood at the eave overhangs provides a clean, paintable surface
DSC_3974_alt1
unit D ends just past the blue barrel, our master suite is beyond

DSC_4278_alt1

 

As is often the case, a few late-in-the-game changes were needed based on an in-person review of the layout. Below is an official “change-order” worked out with the lead framer on site.

20151203_140108_alt1

DSC_4273_alt1

DSC_4284_alt1

And here’s a few pulled-back views of the (nearly) completed envelope:

DSC_4220_alt1
NW corner from the street
DSC_4098_alt1
deck level courtyard looking north
DSC_4083_alt1
Unit B and the old oak tree
DSC_4226_alt1
from the SE corner of the site – the perimeter railing at the roof is temporary

DSC_4223_alt1

 

The last few interior walls should be finishing up tomorrow. We’ve got a heck of a month ahead of us: window and door installation, rough-in mechanical/electrical/plumbing, fire sprinklers and building wrap all need to finish up before we can insulate and close up the walls. Drywall is slated to start the last week of January.

Ready…go!

 

1 Comment

Submit a comment